A At the start of the shift when work is to be carried out
B Every seven days
C Once a month
D When it is more than 2 m deep
Correct Answer: A At the start of the shift when work is to be carried out
A Hot-work permit
B Permit to work
C Risk assessment
D Safety policy
E Scaffolding permit
Correct Answer: B Permit to work, C Risk assessment
A A COSHH assessment
B A gas free certificate
C An environmental assessment
D An isolation certificate
Correct Answer: B A gas free certificate
A The construction phase plan
B The demolition toolbox talk
C The health and safety file
D The pre-tender health and safety plan
Correct Answer: A The construction phase plan
A The Health and Safety Executive (HSE)
B The electricity supply company
C The fire service
D The land owner
Correct Answer: B The electricity supply company
A Cut down at corners and collapse in sections
B Undercut the wall at ground level
C Work across in even courses from the ceiling down
D Work from the doorway at full height
Correct Answer: C Work across in even courses from the ceiling down
A Cut the pipe or cable to see if it's live
B Fill in the hole
C Get the machine driver to dig it out
D Stop work until the situation has been resolved
Correct Answer: D Stop work until the situation has been resolved
A The machine stops automatically if the operator lets go of the controls
B The operator is protected from falling objects
C The reach is limited when working near to live overhead cables
D The speed is limited when tracking over hard surfaces
Correct Answer: B The operator is protected from falling objects
A They should not use it and make sure that no-one else can
B They should only use it for small lifts under 1 tonne
C They should only use it for up to half its safe working load
D They should report the defect at the end of the day
Correct Answer: A They should not use it and make sure that no-one else can
A Date next test is due
B Date of manufacture
C Name of maker
D Safe working load
Correct Answer: D Safe working load
A It gives half the maximum weight to be lifted
B It is a guide figure that may be exceeded slightly
C It may be exceeded by 10% only
D It must never be exceeded
Correct Answer: D It must never be exceeded
A Safe working level
B Safe working load
C Satisfactory weight limit
D Satisfactory working limit
Correct Answer: B Safe working load
A A competent person carries out an asbestos survey
B Employ a licensed asbestos remover
C Notify the Health and Safety Executive (HSE) of the possible presence of asbestos
D Remove and dispose of the asbestos
Correct Answer: A A competent person carries out an asbestos survey
A Change out of dirty clothes
B Do not smoke
C Rinse your mouth with clean water
D Wash your hands and face
Correct Answer: D Wash your hands and face
A Cold cutting fuel tanks
B Cold cutting lead-covered cable
C Hot cutting coated steel
D Stripping lead sheeting
Correct Answer: C Hot cutting coated steel
A They should be ignored as they will get flattened during the demolition
B They should be opened to check if the contents are flammable
C They should be put in the nearest waste skip
D Work should be stopped until they have been safely dealt with
Correct Answer: D Work should be stopped until they have been safely dealt with
A A competent person to supervise the work
B A quantity surveyor to price the extras
C A safety officer to check on health and safety compliance
D A sub-contractor to strip out the buildings
Correct Answer: A A competent person to supervise the work
A Ensuring a competent demolition contractor is selected
B Ensuring methodologies used on site follow the contractor's method statement requirements
C Ensuring task and area specific inductions are carried out
D Ensuring the contractor has a licence to remove asbestos
Correct Answer: D Ensuring the contractor has a licence to remove asbestos
A A Health and Safety Executive (HSE) factory inspector
B A structural engineer
C Another demolition contractor
D The company safety adviser
Correct Answer: B A structural engineer