You need to answer at least 17 out of 19 questions correctly to pass the CSCS Demolition Test for Managers and Professionals. Answers may be reviewed after each question or at the end of the test. Good luck!
CSCS Demolition Mock Test Quick View
Click the question box to reveal the correct answer. You can print the CSCS Demolition Mock Test questions and answers by clicking the printer icon below.
1. When do the Construction (Design and Management) Regulations require an excavation to be inspected by a competent person?
Give one answer
B
C
D
Correct Answer: A
2. Which TWO of the following documents refer to the specific hazards associated with demolition work in confined spaces?
Give two answers
B
C
D
E
Correct Answer: B , C
3. What should be obtained before safely carrying out the demolition cutting of fuel tanks?
Give one answer
B
C
D
Correct Answer: B
4. Where would you find out the method for controlling identified hazards on a demolition project?
Give one answer
B
C
D
Correct Answer: A
5. Who should be consulted before demolition is carried out ? ? near to overhead cables?
Give one answer
B
C
D
Correct Answer: B
Correct Answer: C
7. What should a contractor do if they discover underground services not previously identified?
Give one answer
B
C
D
Correct Answer: D
Correct Answer: B
B
C
D
Correct Answer: A
Correct Answer: D
11. Which of the following is TRUE in relation to the safe working load of a piece of equipment?
Give one answer
B
C
D
Correct Answer: D
Correct Answer: B
13. When asbestos material is suspected in buildings to be demolished, what is the FIRST priority?
Give one answer
B
C
D
Correct Answer: A
14. After exposure to lead, what precautions should you take before eating or drinking?
Give one answer
B
C
D
Correct Answer: D
15. What is the MOST common source of high levels of lead in the atmosphere during demolition work of an old building?
Give one answer
B
C
D
Correct Answer: C
16. What action should be taken if the contractor discovers ? ? unlabelled drums or containers on site?
Give one answer
B
C
D
Correct Answer: D
17. Who MUST be the FIRST person a demolition contractor appoints before undertaking demolition operations?
Give one answer
B
C
D
Correct Answer: A
18. Which of the following does NOT ensure good health and safety standards on a demolition project?
Give one answer
B
C
D
Correct Answer: D
19. If there are any doubts about a building's stability, who should a demolition contractor consult?
Give one answer
B
C
D
Correct Answer: B