Health Safety and Environment Test for Managers and Professionals

You have 45 minutes to answer 50 multiple choice CSCS Health, Safety and Environment Test questions for Managers and Professionals. You need to answer at least 46 out of 50 questions correctly to pass. Answers may be reviewed after each question or at the end of the test. Good luck!

Tests Taken

Last Score

Average Score

Your Progress

1677 votes - average 4.8 out of 5

Health Safety and Environment Test for Managers and Professionals Quick View

Click the question box to reveal the correct answer. You can print the Health Safety and Environment Test for Managers and Professionals questions and answers by clicking the printer icon below.

A By iron weights suspended from the frame by chains or other strong material
B By roping them to concrete blocks or kerb stones
C To prevent them being stolen
D With built-in weights where possible
Correct Answer: D With built-in weights where possible
A They should not use it and make sure that no-one else can
B They should only use it for small lifts under 1 tonne
C They should only use it for up to half its safe working load
D They should report the defect at the end of the day
Correct Answer: A They should not use it and make sure that no-one else can
A A suitable site induction that is specific to the site and to their work
B Confirmation of their working hours and rest breaks
C Details of the client brief and project expectations
D Details of the designer's plan of work
E Information about relevant hazards and control measures
Correct Answer: A A suitable site induction that is specific to the site and to their work, E Information about relevant hazards and control measures
A A statement by the client
B Form F10 or a notice carrying the specified information
C Notice of application to erect hoardings
D Notice of the principal contractor's health and safety policy
Correct Answer: B Form F10 or a notice carrying the specified information
A At the start of the shift
B Every seven days
C Once a month
D When it is more than 2 m deep
Correct Answer: A At the start of the shift
A For one week on site, before sending them to head office
B For three months after the inspection has been carried out
C Until the project is completed
D Until the project is completed and then for three months
Correct Answer: D Until the project is completed and then for three months
A The arrangements for carrying out the demolition or dismantling
B The demolition or dismantling specification
C The pre-tender demolition or dismantling health and safety plan
D The revised information for the health and safety file
Correct Answer: A The arrangements for carrying out the demolition or dismantling
A Instruct the tradesperson to build the detail as best they can
B Make sure the issue is raised with the person responsible for the design
C Substitute the detail with components which could work without consulting the person responsible for the design.
D Use your experience and build it as you think it should be done
Correct Answer: B Make sure the issue is raised with the person responsible for the design
A No, because plasterboard is hazardous waste
B No, because plasterboard should not be mixed with other wastes
C Yes, because plasterboard is not hazardous waste
D Yes, because the boards will only be a small proportion of the skip content
Correct Answer: B No, because plasterboard should not be mixed with other wastes
A Completing a permit to work form
B Ensuring that a safe system of work has been identified and is followed
C Entering slowly and breathing shallowly until you are sure the air is good to breathe
D Informing your office before entering
E Making sure that emergency rescue arrangements are in place
Correct Answer: B Ensuring that a safe system of work has been identified and is followed, E Making sure that emergency rescue arrangements are in place
A A caution or prosecution by the police wildlife crimes officer
B A prohibition notice issued by the Health and Safety Executive (HSE)
C A visit from an RSPCA inspector
D Prosecution by the RSPB
Correct Answer: A A caution or prosecution by the police wildlife crimes officer
A Ensure that the material is removed and tree protection fencing is placed around the tree to prevent further damage
B Ensure that the material is removed if the tree looks damaged
C Ensure that the tree is watered regularly until the materials are removed
D Nothing, materials can be stored anywhere
Correct Answer: A Ensure that the material is removed and tree protection fencing is placed around the tree to prevent further damage
A Ask others if they feel dizzy. If they don't then carry on for five minutes
B Have a drink, it's the first sign of dehydration
C Make sure that you and any others get out quickly and report it
D Sit down, put your head between your knees and take deep breaths to get some oxygen back into your system
Correct Answer: C Make sure that you and any others get out quickly and report it
A Carry on working but do not use electrical tools
B Carry on working but take plenty of breaks in the fresh air
C Get out of the confined space immediately
D Switch off the alarm
Correct Answer: C Get out of the confined space immediately
A To let the public know what you are doing
B To minimise the number of people below at any one time
C To provide alternative routes for the public and keep them away from the area
D To provide netting to prevent falling objects
Correct Answer: C To provide alternative routes for the public and keep them away from the area
A Leave the cord alone and report the problem to the contractor
B Tell the contractor that you are going to untie the cord
C Untie the cord, but ask the contractor to re-tie it when you have finished
D Untie the cord, carry out your work and tie it up again
Correct Answer: A Leave the cord alone and report the problem to the contractor
A Ask them to go and see if they can get hold of a harness and lanyard
B Ask them to stop work and report it to the site manager
C Ask them to tie the damaged edges together using the net test cords
D Ask them to work somewhere away from the damaged area of net
Correct Answer: B Ask them to stop work and report it to the site manager
A Four scaffold boards wide
B Suitable and sufficient for the job in hand
C Three scaffold boards wide
D Two scaffold boards wide
Correct Answer: B Suitable and sufficient for the job in hand
A Educate the workforce to be more careful while working at height
B Ensure that design and construction solutions eliminate the need for working at height
C Ensure that details of risky operations are included in the construction phase health and safety plan
D Leave the decisions on how to work at height to the principal contractor
Correct Answer: B Ensure that design and construction solutions eliminate the need for working at height
A Ask for the bottom of the ladder to be wedged with blocks of wood
B Ask someone to stand with their foot on the bottom rung
C Ensure that it is tied at the top
D Tie it at the bottom
Correct Answer: C Ensure that it is tied at the top
A The plant operators will be given strict instructions on which route they must take
B The site manager will direct all pedestrians away from traffic routes
C The traffic routes will be shown on the site notice or hazard board
D There will be physical barriers between traffic and pedestrian routes
Correct Answer: D There will be physical barriers between traffic and pedestrian routes
A Barriers to keep pedestrians away from mobile plant and vehicles
B One-way systems
C Pedestrians and mobile plant using the same routes
D Speed limits
Correct Answer: C Pedestrians and mobile plant using the same routes
A At any time
B Only if it is designed to carry passengers
C Only if it is raining
D Only if they have a long way to go
Correct Answer: B Only if it is designed to carry passengers
A 110 volt extension reels
B 230 volt power tools
C Poor housekeeping and build up of waste
D Timber racks
E Uncontrolled hot works
Correct Answer: C Poor housekeeping and build up of waste, E Uncontrolled hot works
Correct Answer: A Gates, E Warning signs
A It shows that the tool has been PAT tested within the past 12 months
B It shows that the tool is waterproof and can be used outdoors in wet conditions
C It shows that the tool runs off a 110 volt supply
D It shows that the tool runs off a 230 volt supply and should not be used on site
Correct Answer: C It shows that the tool runs off a 110 volt supply
Correct Answer: C , D
A The cylinder is full
B The cylinder is nearly empty
C The valve is leaking
D You must lay the cylinder on its side
Correct Answer: C The valve is leaking
A They must be connected to the heat source by flexible rubber tubing
B They must be located inside the cabin but away from the heat source
C They must be located outside the cabin
D They must be lying on their side
Correct Answer: C They must be located outside the cabin
A Safety gloves do not need to be worn
B Safety gloves must be worn
C You must carry safety gloves at all times
D You must carry safety gloves at all times
Correct Answer: B Safety gloves must be worn
A Black
B Green
C Maroon
D Orange
Correct Answer: C Maroon
A Ask another worker to get a forklift truck
B Make sure that they do not move the load until a safe method is identified
C Tell them to lift and move the load quickly to avoid injuring themselves
D Tell them to try to lift it using the correct lifting methods
Correct Answer: B Make sure that they do not move the load until a safe method is identified
A The COSHH assessment
B The delivery note
C The manual handling assessment
D The site diary
Correct Answer: A The COSHH assessment
A Do not use it as the substance is poisonous
B Find out what hand cleaner you will need as the substance will not wash off easily
C Find out what protection you need as the substance is corrosive and can damage your skin upon contact
D Wash your hands after you have used the substance
Correct Answer: C Find out what protection you need as the substance is corrosive and can damage your skin upon contact
A Tell them not to wear them, and to work without any hearing protection
B Tell them they cannot work in any noisy area until they are replaced
C Tell them to put them on and go on to site with them as they are
D Tell them to take an ear pad from another set of ear defenders
Correct Answer: B Tell them they cannot work in any noisy area until they are replaced
A To assist in the management of any asbestos in a building
B To estimate how much it would cost to remove any asbestos
C To identify all asbestos materials that need to be removed before demolition or refurbishment work
D To provide accurate information on the location, amount and condition of asbestos materials
Correct Answer: B To estimate how much it would cost to remove any asbestos
A Makes you hear better
B Reduces damaging noise to an acceptable level
C Repairs your hearing if it is damaged
D Stops you hearing all noise
Correct Answer: B Reduces damaging noise to an acceptable level
A In a large indoor space
B In a small room
C Outside on a still day
D Outside on a windy day
Correct Answer: B In a small room
A Ask the injured person what happened
B Check that you are not in any danger before you check the injured person
C Move the injured person to a safe place
D Tell the site manager
Correct Answer: B Check that you are not in any danger before you check the injured person
A Tell them to carry on working to exercise the hand
B Tell them to put the hand into cold water or under a cold running tap
C Tell them to rub barrier cream or Vaseline into the burn
D Tell them to wrap a handkerchief around the burn
Correct Answer: B Tell them to put the hand into cold water or under a cold running tap
A By asking someone on site
B By attending a first-aid course
C By looking for the first-aid sign
D It should be included at site induction
Correct Answer: D It should be included at site induction
A Dial 999 and ask for an ambulance
B Phone the electricity company
C Pull them away from the cable
D Switch off the power and call for help
Correct Answer: D Switch off the power and call for help
A A WC toilet pan
B A boiler operating at a temperature of 80°C
C A cold water storage cistern containing water at 10°C
D An infrequently used shower hose outlet
Correct Answer: D An infrequently used shower hose outlet
A To enable tools and equipment to be properly checked before work starts
B To ensure that the job is being carried out properly
C To ensure that the job is carried out by the easiest method
D control work to prevent a major accident
Correct Answer: D control work to prevent a major accident
A Erecting security fencing or hoarding and keeping all entrance gates closed
B Giving safety talks to the local schools and youth clubs
C Putting up 'keep out' posters
D Sending a flyer to local households telling them to keep their children off site
Correct Answer: A Erecting security fencing or hoarding and keeping all entrance gates closed
A A type of barrier or machine guard
B Anything that has the potential to cause harm or damage
C The level of risk on site
D The likelihood that something might happen
Correct Answer: B Anything that has the potential to cause harm or damage
A Legislation does not apply to anyone under 18 years of age
B There is no legal duty to provide them with personal protective equipment (PPE)
C They are usually left to work alone to gain experience
D They have less experience and may not recognise danger or understand what could go wrong
Correct Answer: D They have less experience and may not recognise danger or understand what could go wrong
A Educate, reduce, isolate, control
B Eliminate, reduce, isolate, control
C Employ, reduce, isolate, control
D Ensure, reduce, isolate, control
Correct Answer: B Eliminate, reduce, isolate, control
A It contains the contents of the risk assessments
B It tells them how health and safety is managed within their organisation
C It tells them how to do their job safely
D It tells them how to use tools and equipment safely
Correct Answer: B It tells them how health and safety is managed within their organisation